THE LEGACY DINING HALL

DH rendering front.jpg

The dining hall is the heart of Pine Valley where much activity and connection occur year-round. It provides a warm and safe family atmosphere for our campers where their physical needs are met which builds a bridge to deeper connections with them.  This building will be a strategic gathering place for fun activities and meaningful conversations around the tables and will allow us to point kids to a loving heavenly Father who delights to meet their deepest and most basic needs.  This 12,000 square ft building will feature a family room entry, dining space to seat 300, commercial kitchen, bathrooms, nurse’s office, storage, wrap-around porch with additional seating, and second floor offices. 

October 1, 2024 Update:

On January 16th we started to build our trusses: 

  • Preparation to pour the floor began on Feb 15th

  • Plumbing & utilities installation - March

  • Thermal barrier - April

  • Insulation installation – April

  • Floor Poured April 29th

  • Steel Delivery June 3rd

  • Trusses moved June 11th

  • Steel erection June 3rd – July 1st

  • Steel decking down for 2nd floor July 10th

 

Next steps:

  1. Prep and pour cement 2nd Floor offices - DONE! Sept 3-11

  2. Build walls, install trusses for both Dining Hall and Office – started Sept 23

  3. Complete roof: shiplap, wiring, insulation, sheeting, and metal roof. Install solar.

  4. Close in the kitchen and office envelope which consists of siding, wiring, insulation, shiplap, drywall & prime, stain floors, finish trim & doors.

  5. Raise more funds as existing cash will be spent. Wait on the Lord!

A view of the inside
01:02
Kitchen work area
01:19
The windows
00:32
A tour of the entrance
00:57
Overhead Door garage doors
00:41
Dining Hall Site Update
00:39
Up Close View
00:52